Berthing Projects:


INSTALLATION REQUIREMENTS:
a. Replace berths with CPO modular berths with privacy partitions and berth curtains arranged in six-person cubicles, as practical, with ten percent long berths. Total number of new berths will be equal to the existing berthing.
b. Redistribute air supply terminals to provide overhead diffusers within each berth cubicle.
c. Redistribute overhead lighting to conform to new arrangements. Provide one berth light per accommodation and mirror lights as required.
d. Improve traffic flow and privacy, as practical, through the arrangement of furniture.
e. Provide lockers for stowage of clothing and personal effects to meet or exceed minimums required per accommodations. For CPO (E7-E9) provide 14 cubic feet of locker space, 18 inches hanging space and 0.75 cubic feet of soiled laundry stowage.
f. Provide a means of secondary egress if one does not exist and berthing capacity exceeds 21 personnel.
g. Provide recreation/lounge area in berthing compartments segregated from sleeping area to the maximum extent feasible.
h. Provide storage for iron and ironing board.
i. Provide bulletin boards, watch-quarter boards and mirrors.
j. Prepare and preserve decks, bulkheads and overheads.
k. Replace deck covering.
l. Replace any damaged insulation.
m. Paint bulkheads and overheads.


INSTALLATION REQUIREMENTS:
a. Replace berths with modular berths with privacy partitions and berth curtains arranged in six-person cubicles, as practical, with ten percent long berths. Total number of new berths will be equal to the existing berthing.
b. Redistribute air supply terminals to provide overhead diffusers within each berth cubicle.
c. Redistribute overhead lighting to conform to new arrangements. Provide one berth light per accommodation and mirror lights as required.
d. Improve traffic flow and privacy, as practical, through the arrangement of furniture.
e. Provide lockers for stowage of clothing and personal effects to meet or exceed reference (a).
f. Provide a means of secondary egress if one does not exist and berthing capacity exceeds 21 personnel.
g. Provide recreation/lounge area in berthing compartments segregated from sleeping area to the maximum extent feasible
h. Provide storage for iron and ironing board.
i. Provide bulletin boards, watch-quarter boards and mirrors.
j. Prepare and preserve decks, bulkheads and overheads.
k. Replace deck covering.
l. Replace any damaged insulation.
m. Paint bulkheads and overheads.

INSTALLATION REQUIREMENTS:
a. Replace berths with CPO style berths with privacy partitions and berth curtains arranged in six-man cubicles, as practical, with ten percent long berths. Total number of new berths will be equal to the existing berthing.
b. Redistribute air supply terminals to provide overhead diffusers for each berth cubicle and modify recirculation system ducting to suit.
c. Redistribute overhead lighting to conform to new arrangements. Provide one berth light per accommodation and mirror lights as required.
d. Improve traffic flow and privacy, as practical, through the arrangement of furniture.
e. Provide lockers for stowage of clothing and personal effects to meet or exceed minimums required per accommodation in accordance with reference (a).
f. Provide a means of secondary egress if one does not exist and berthing capacity exceeds 21 personnel.
g. Provide recreation/lounge area in berthing compartment segregated from sleeping area to the maximum extent feasible
h. Relocate existing rifle racks and helmet racks to suit new furniture and arrangements, if applicable.
i. Provide adequate facilities for field pack stowage.
j. Provide stowage for iron and ironing board.
k. Provide bulletin boards, watch-quarter boards and mirrors.
l. Prepare and preserve decks, bulkheads and overheads.
m. Replace deck covering.
n. Replace any damaged insulation.
o. Paint overheads and bulkheads.


INSTALLATION REQUIREMENTS:
a. Replace berths with modular berths with privacy partitions and berth curtains arranged in six-person cubicles, as practical, with ten percent long berths. Total number of new berths will be equal to existing berthing.
b. Redistribute air supply terminals to provide overhead diffusers for each berth cubicle and modify recirculation system ducting to suit.
c. Redistribute overhead lighting to conform to new arrangements. Provide one berth light per accommodation and mirror lights as required.
d. Improve traffic flow and privacy, as practical, through the arrangement of furniture.
e. Provide lockers for stowage of clothing and personal effects to meet or exceed minimums required per accommodation in accordance with reference (a).
f. Provide a means of secondary egress if one does not exist and berthing capacity exceeds 21 personnel.
g. Provide recreation/lounge area in berthing compartment segregated from sleeping area to the maximum extent feasible
h. Relocate existing rifle racks and helmet racks to suit new furniture and arrangements, if applicable.
i. Provide adequate facilities for field pack stowage.
j. Provide stowage for iron and ironing board.
k. Provide bulletin boards, watch-quarter boards and mirrors.
l. Prepare and preserve decks, bulkheads and overheads.
m. Replace deck covering.
n. Replace any damaged insulation.
o. Paint overheads and bulkheads.


INSTALLATION REQUIREMENTS:
a. Replace berths. Total number of new berths shall be equal to the number of existing berth accommodations. One man or two man berths will be a new replacement, and 3-man berths will be an improved full width unit with privacy curtains.
b. Improve traffic flow and privacy, as practical, through the arrangement of furniture.
c. Provide secretaries and lockers for stowage of clothing and personal effects to meet or exceed minimums required per accommodation in accordance with reference (a). Secretaries include a new safe.
d. Provide stainless steel sink unit with storage space above and below sink and with improved faucet and drain components.
e. Provide chairs.
f. Replace joiner doors.
g. Provide accessories and additional shelves, working surfaces and stowage as feasible.
h. Replace ventilation diffusers, and as feasible improve distribution of air.
i. Redistribute overhead lighting to conform to new arrangements. Provide one berth light per accommodation and mirror lights at each sink. Lights within secretaries will include a receptacle.
j. Prepare and preserve decks, bulkheads and overheads.
k. Replace deck covering.
l. Replace any damaged insulation.
m. Paint overheads and bulkheads.

Sanitary Projects:


INSTALLATION REQUIREMENTS:
a. Remove and replace fixtures in quantities to meet habitability standards. Rearrange to provide required clearances, privacy and access.
b. Install new Stainless Steel countertop lavatory units.
c. Install new Stainless Steel water closet partitions supported from the overhead and bulkhead.
d. Install new Stainless Steel urinal supports and dividers, if applicable.
e. Install new Stainless Steel shower partitions and, if space permits, drying areas.
f. Install new accessories.
g. Replace joiner doors.
h. Replace electrical heaters
i. Install cleaning gear locker and service sink or bucket fill area with garden hose connection where practical.
j. Modify piping to suit new arrangement and replace any deteriorated piping.
k. Modify the ventilation distribution system for efficiency and to suit new arrangement.
l. As space permits, either enclose or insulate any water heater located within space.
m. Install improved lighting and receptacles to accommodate the new arrangement.
n. Install new porcelain tile deck covering.
o. Prepare and paint the sanitary space


INSTALLATION REQUIREMENTS:
a. Remove and replace fixtures in quantities to meet habitability standards. Rearrange to provide required clearances, privacy and access.
b. Install new Stainless Steel countertop lavatory units.
c. Install new Stainless Steel water closet partitions supported from the overhead and bulkhead.
d. Install new Stainless Steel urinal supports and dividers, if applicable.
e. Install new Stainless Steel shower partitions and, if space permits, drying areas.
f. Install new accessories.
g. Replace joiner doors.
h. Replace electrical heaters
i. Install cleaning gear locker and service sink or bucket fill area with garden hose connection where practical.
j. Modify piping to suit new arrangement and replace any deteriorated piping.
k. Modify the ventilation distribution system for efficiency and to suit new arrangement.
l. As space permits, either enclose or insulate any water heater located within space.
m. Install improved lighting and receptacles to accommodate the new arrangement.
n. Install new porcelain tile deck covering.
o. Prepare and paint the sanitary space


INSTALLATION REQUIREMENTS:
a. Remove and replace fixtures in quantities to meet habitability standards. Rearrange to provide required clearances, privacy and access.
b. Install new Stainless Steel countertop lavatory units.
c. Install new Stainless Steel water closet partitions supported from the overhead and bulkhead.
d. Install new Stainless Steel urinal supports and dividers, if applicable.
e. Install new Stainless Steel shower partitions and, if space permits, drying areas.
f. Install new accessories.
g. Replace joiner doors.
h. Replace electrical heaters
i. Install cleaning gear locker and service sink or bucket fill area with garden hose connection where practical.
j. Modify piping to suit new arrangement and replace any deteriorated piping.
k. Modify the ventilation distribution system for efficiency and to suit new arrangement.
l. As space permits, either enclose or insulate any water heater located within space.
m. Install improved lighting and receptacles to accommodate the new arrangement.
n. Install new porcelain tile deck covering.
o. Prepare and paint the sanitary space


INSTALLATION REQUIREMENTS:
a. Remove and replace fixtures in quantities to meet habitability standards. Rearrange to provide required clearances, privacy and access.
b. Install new Stainless Steel countertop lavatory units.
c. Install new Stainless Steel water closet partitions supported from the overhead and bulkhead.
d. Install new Stainless Steel urinal supports and dividers, if applicable.
e. Install new Stainless Steel shower partitions and, if space permits, drying areas.
f. Install new accessories.
g. Replace joiner doors.
h. Replace electrical heaters
i. Install cleaning gear locker and service sink or bucket fill area with garden hose connection where practical.
j. Modify piping to suit new arrangement and replace any deteriorated piping.
k. Modify the ventilation distribution system for efficiency and to suit new arrangement.
l. As space permits, either enclose or insulate any water heater located within space.
m. Install improved lighting and receptacles to accommodate the new arrangement.
n. Install new porcelain tile deck covering.
o. Prepare and paint the sanitary space


INSTALLATION REQUIREMENTS:
a. Remove and replace fixtures in quantities to meet habitability standards. Rearrange to provide required clearances, privacy and access.
b. Install new Stainless Steel countertop lavatory units.
c. Install new Stainless Steel water closet partitions supported from the overhead and bulkhead.
d. Install new Stainless Steel urinal supports and dividers, if applicable.
e. Install new Stainless Steel shower partitions and, if space permits, drying areas.
f. Install new accessories.
g. Replace joiner doors.
h. Replace electrical heaters
i. Install cleaning gear locker and service sink or bucket fill area with garden hose connection where practical.
j. Modify piping to suit new arrangement and replace any deteriorated piping.
k. Modify the ventilation distribution system for efficiency and to suit new arrangement.
l. As space permits, either enclose or insulate any water heater located within space.
m. Install improved lighting and receptacles to accommodate the new arrangement.
n. Install new porcelain tile deck covering.
o. Prepare and paint the sanitary space

Repair Projects:

CRPR Repairs of Chief Petty Officer's Berthing and Sanitary Spaces

ERPR Repairs of Crew's Berthing and Sanitary Spaces

NRPR Repairs of Staff Non-Commissioned Officer's Berthing and Sanitary Spaces

TRPR Repairs of Troop Berthing and Sanitary Spaces

ORPR Repairs of Officer's Staterooms and Sanitary Spaces

MRPR Miscellaneous Repair Project